EPF-Lausanne/8 September 2008

From 2008.igem.org

(Difference between revisions)
 
(One intermediate revision not shown)
Line 1: Line 1:
[https://2008.igem.org/wiki/index.php?title=EPF-Lausanne/7_September_2008 <<Previous] - [https://2008.igem.org/Team:EPF-Lausanne/Notebook Back to Notebook] -  
[https://2008.igem.org/wiki/index.php?title=EPF-Lausanne/7_September_2008 <<Previous] - [https://2008.igem.org/Team:EPF-Lausanne/Notebook Back to Notebook] -  
-
[https://2008.igem.org/wiki/index.php?title=EPF-Lausanne/9_September_2008 Next>>]
+
[https://2008.igem.org/wiki/index.php?title=EPF-Lausanne/11_September_2008 Next>>]
==Ligations==
==Ligations==
Line 19: Line 19:
Modelling: Thomas
Modelling: Thomas
 +
 +
==Notebook==
 +
 +
with the courses starting soon for most of the team members, notebook will only be updated approx. once a week.

Latest revision as of 14:55, 27 October 2008

<<Previous - Back to Notebook - Next>>

Ligations

CD and BC1 were succesful.

Lab meeting

We discussed the issue with the self-signaling. We come to the decision that we need to integrate a bistable switch, ie. that each path auto-activates itself and represses the other.

To achieve that we need to add LacIm after the RFP and CI after the GFP. We will add the LacIm into the plasmid immediately, but will wait with the CI as we first want to finish what we begun. (We would have to start over again for the CI).

We appointed task leaders for the following weeks. They will coordinate the efforts:

Cloning: Gilles

Microfluidics: Nicolas

Modelling: Thomas

Notebook

with the courses starting soon for most of the team members, notebook will only be updated approx. once a week.